Electrical and Plumbing

Several days this past week, I went down to the construction site and close to 20 people were working.  Several guys were working on the second section of the retaining wall, the masons have almost completed their work on the stone exterior, the framers started putting windows in.  They have all the square windows and the window/doors on the mezzanine installed.  They have saved the challenging round windows for last.  The plumbers have been insulating pipe and the electricians have been running wires.  The next big step is to get the exterior walls insulated with spray foam.  That work is scheduled for Monday, April 16th.  All teams are working hard to have their piece complete.